Improvement of the East Quay Barcelona Port . Phase 2.
Barcelona
Location: Barcelona (Spain)
Developer: Port Authority of Barcelona
Budget: 21.398.981,61 €
Execution time: 19 months
Characteristics
The works consisted in the repair and improvement of the breakwater, parallel to shore ,over a length of more than 5 km.
The main actions corresponded with:
Repair of breakwater slope and foot with rockfill.
Protection berms in slope foot with rocks and 10 ton concrete cubic blocks.
New slope protection over existing one, formed by concrete blocks of 50 tons
The key figures of the works are:
Supplies and placement riprap 4 tons: 114.963 Tn.
Riprap material recovery from existing quaids: 48.353 Tn.
Supplies and placement riprap 500-1.000 kg: 3.456 Tn.
Concrete in blocks of 50 tons: 122.743 m³.
Concrete in blocks of 10 tons: 6.835 m³.
Transport and placement, blocks of 50 tons: 5.713 uds.
Transport and placement, blocks of 10 tons: 1.608 uds.
Home > Proyects > Protection Works > Improvement of the East Quay Barcelona Port . Phase 2.
Protection works are the construction of structures in the sea to protect areas for future ports from sea swell. They protect docking and jetty operations, the loading and unloading of ships, as well as any other manoeuvre, storage, service, facilities and access routes which occur inside the area.
View all
Valencia Port south enlargement end of breakwater redevelopment
Valencia

Breakwater – Quay extension in Punta Sollana
Bilbao

Sheltering works for Valencia Port enlargement
Valencia

Valencia Port enlargement, Southern Dock and Quay Line, Phase I
Valencia

Sheltering works for Sagunto Port enlargement
Valencia

Improvement of the East Quay Barcelona Port . Phase 2.
Barcelona

Punta Lucero end of breakwater blocks replacement
Bilbao

Valencia Port south enlargement end of breakwater redevelopment
Valencia

Breakwater – Quay extension in Punta Sollana
Bilbao

Sheltering works for Valencia Port enlargement
Valencia

Valencia Port enlargement, Southern Dock and Quay Line, Phase I
Valencia