Valencia Port outer dock mooring distribution, installations and provisional pavements (America’s Cup 2007)
Valencia
Location: Valencia (Spain)
Developer: Valencia Port Authority and Consorcio Valencia 2007
Budget: 29.516.770,07 €
Execution time: 12 months
Characteristics
Urbanization, paving and new mooring berths installation. The two basins generated shelter fixed and floating pontoons, separated by a low-reflectivity quay wall caisson. Furthermore, a heliport and other accesses are executed.
The key figures of the works are:
Dredging Trench: 208.576 m3
Level space granular filling: 56.133 m3
Rubble mound bedding layer and breakwaters, riprap: 150.000 t
Reinforced Concrete floating caissons: 8 uts.
6-22 tons blocks: 4.097 m3
Quay Superstructure: 425 m
Mooring line: 2.438 m
Floating pontoons
146 Piles up to Ø609,6 mm
21 Piles up to Ø508 mm
Fixed reinforced concrete jetty: 223 m
Gangways: 20 uts.
Number of berths:
South (length 10-50 m): 455 uts.
North (length 15-35 m): 168 uts.
Road pavements and heliport
General Installations